Dear Project Officer; In order for your product to start up in a timely and healthy manner, please check the “Yes” or “No” boxes by examining the questions below. Make sure to review the assembly diagram in the user and assembly manual or which you will request from ACS. If this form is not delivered to ACS Technical Service at least 7 working days before your start up date, the start up process does not start. When our team arrives at your worksite, if the start up conditions are not ready or missing, the process of start up for the second time will be made with a fee. If you need extra information about this form or your device, ACS will gladly support you. Best wishes for a successful business together.
If the products replaced in the spots in the project
If the connection of the air handling unit cells in such a way that they are balanced on a very smooth surface and that air is not leaked
If all the wiring(and all related cableworks) have to be completed as per manufacturer’s technical specifications
Heating and Cooling Coils must be equipped with three way valves and servo motors. And water supply must be started
Cleaning of units must have been done (Scraps and deposits accumulated during construction)
If there are VAV units and if it is requested connection of these to BMS all electric wiring must have beeen done untill automation control board.
If there is duct type electric heater , proper cable must have been installed between electric Resistance and AHU automation control panel.
If there are VAV or electric heater in ceiling ,proper service door (min 60×60 cm) must have been installed on the ceiling .
Drain water and siphon connections must be done
All staff who will be trined for use of the units must be ready
Note: Additional training will be under extra fee